Salient
features of National Waterway No. 4 - Godavari & Krishna rivers
& Canals between Kakinada and Puducherry (NW-4)
Declared
as National Waterway 4 (NW 4) on 25.11.2008
Detailed Project Report (DPR)
prepared by M/s. WAPCOS
Total Length - 1027 km.
River
portion (328 km),
Irrigation canals (302 km)
salt water canals (397 km)
Estimated
Cost (at 2009 prices)- Rs 1515 Cr
Phase - 1 - Rs. 609 crore
Development of stretch comprising of Godavari & Krishna rivers,
and Kakinada & Eluru canals, which has maximum cargo potential,
at an estimated cost of Rs.390 Crore & land acquisition for remaining
stretch at an estimated cost of Rs.219 crore
Phase
- 2 - Rs .906 crore
Development of North & South Buckingham Canal, Commamur canal
& Kaluvelly Tank at an estimated cost of Rs.906 crore
Period
of Completion - 7 years
Land
Acquisition
in
Tamil Nadu - 300 Ha
in Andhra Pradesh -1380 Ha
in Puducherry - 27 Ha
Estimated cost of land acquisition - Rs. 391 Crore
Details
of dredging:
in canals - 20 million cum at an estimated cost of Rs. 333 Crore
Potential Cargo - 11 million tonne per annum
Coal on Godavari river,
cement on Krishna river
rice in both Krishna and Godavari
EIRR
Phase - I 34.63%
Entire waterway 16.12%
For
Executive Summary of DPR click here